|  Outline
of Town Building Scheme ProjectsLAND PURCHASE
AND DEVELOPMENT METHOD HUD started to purchase
land in July 1966 and acquired about 1,800 ha(2,600 landowners)by October of 1973
with the help of Ibaraki Prefecture and the 6 towns and villages involved in the
project.
The basic development of the city plan was implemented through
the following three projects as authorized by applicable laws.
COLLECTIVE
GOVERNMENT AND PUBLIC OFFICE FACILITIES PROJECT [GOVENMENT
INSTITUTIONS PROJECT] This project includes purchase and preparation of land,
and construction of buildings for research and educational facilities of the government.
After HUD acquired and prepared the land, the former Ministry of Construction
and the former Ministry of Education built the research and educational institutes.
The area allotted for this project is 1,463 ha.
NEW
URBAN RESIDENTIAL AREA DEVELOPMENT PROJECT To
supply a large number of housing sites with a good living environment systematically,
the entire land for the project housing was purchased, prepared and subdivided
to top-grade private housing sites with complete utilities such as roads, parks,
water supply and sewage system. This project has taken place in 3 zones, in a
total area of approximately 260 ha.
LAND
READJUSTMENT PROJECT This is a project to
create quality building sites by reshaping features of the land while furnishing
public facilities such as roads, parks, water supply and sewage system. HUD has
divided 1,110 ha of land into 10 zones to carry out the project.
|
|